Agenda item
Land off Robert Tressell Close, Hastings
Minutes:
Proposal:
Variation of condition 6 (hard landscaping) and 21 (approved plans) of Planning Permission HS/FA/14/00823
Application No:
HS/FA/16/00710
Existing Use:
Conservation Area:
Listed Building
Public Consultation
Development site
Yes - Blacklands
No
4 letters of objection received
The Principal Planner, Miss Roots, presented this report for the variation of Conditions 6 (hard landscaping) and 21 (approved plans) in respect of the erection of a 2m high retaining wall on the western boundary of the site and to accurately identify the changes in site levels. Members were advised that this was a retrospective application.
Members were advised of an update to the report of 1 further letter of objection that had been received regarding the report and visibility of the wall from the street scene. Miss Roots clarified where the proposed works would be visible from. She advised that the retaining wall was needed to make the adjoining gardens usable for future residents.
Councillor Clarke proposed a motion to approve the application as set out in the resolution below. This was seconded by Councillor Wincott.
RESOLVED - (unanimously) that planning permission be granted subject to the following conditions:-
1.
No development shall take place until the measures outlined in the submitted ecological statements and reports (Land off Robert Tressell Close, Hastings, Ecological Impact Assessment by the Bourne Valley Consultancy dated September 2007; and the update letter from the Bourne Valley Consultancy dated 17 October 2014) have been fully implemented, unless:
(i) the programme for such measures is otherwise specified within that document (for example with regard to measures related to monitoring, further survey work, the erection of bird boxes on buildings or other conservation enhancements), in which case the works shall be carried out in accordance with the timescales contained therein or;
unless the scheme(s), or programme(s) of measures contained within the ecological statements and reports is otherwise first varied, by way of prior written approval from the Local Planning Authority.
2.
(i) Construction of the development shall be carried out in accordance with the approved details of the proposed means of foul sewerage and surface water disposal/management; and
(ii) The dwellings approved shall not be occupied until those works have been completed.
The dwellings shall not be occupied until the Local Planning Authority has confirmed in writing that it is satisfied, that the necessary drainage infrastructure capacity is now available to adequately service the development.
3.
Development shall be carried out in accordance with the details approved under reference HS/CD/15/00867 for a scheme of soft landscaping, which includes indications of all existing trees and hedgerows on the land including details of those to be retained, together with measures for their protection in the course of development (in accordance with BS5837 2012: Trees in relation to design, demolition and construction – Recommendations). The new soft landscaping details include planting plans; written specifications (including cultivation and other operations associated with plant and grass establishment); schedules of plants, noting species, plant sizes and proposed numbers/densities, together with an implementation programme;
4.
All planting seeding or turfing comprised in the approved soft landscaping scheme shall be carried out prior to the occupation of any part of the development, or with the written agreement of the Local Planning Authority, in the first planting and seeding seasons following the occupation of any buildings or the completion of the development, whichever is the sooner. Any trees or plants which within a period of 5 years from the completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority gives written consent to any variation;
5.
Development shall be carried out in accordance with details of the hard landscape works approved under reference HS/FA/16/00867, and further amended under planning permission HS/FA/16/00710. These details include proposed finished levels or contours; means of enclosure; car parking layouts; other vehicle and pedestrian access and circulation areas; hard surfacing materials;
6.
Hard landscaping works shall be carried out prior to the occupation of any part of the development or in accordance with the programme agreed with the Local Planning Authority;
7.
With the exception of internal works the building works required to carry out the development allowed by this permission must only be carried out within the following times:-
08.00 - 18.00 Monday to Friday
08.00 - 13.00 on Saturdays
No working on Sundays or Public Holidays.
8.
The dwellings hereby approved shall not be occupied until provision has been made for high speed broadband infrastructure to serve the development;
9.
The development shall be completed in accordance with the surface water drainage details approved under reference HS/CD/15/00867;
10.
During any form of earthworks and/or excavations that are carried out as part of the development, suitable vehicle wheel washing equipment should be provided within the site, in accordance with the details approved under reference HS/CD/15/00867 to prevent contamination and damage to the adjacent roads;
11.
The development shall not be occupied until parking areas have been provided in accordance with the approved plans and the areas shall thereafter be retained for that use and shall not be used other than for the parking of motor vehicles;
12.
The development shall not be occupied until cycle parking areas have been provided in accordance with the approved plans and the areas shall thereafter be retained for that use and shall not be used other than for the parking of cycles;
13.
During development every loaded lorry shall be covered before leaving the site;
14.
Development shall be implemented in accordance with the approved scheme for pedestrian access improvements between the site and Priory Avenue. The improvements shall be provided prior to the occupation of any of the dwellings approved;
15.
No site clearance or tree or hedge removal shall be carried out on site between the 1st March and 31st July inclusive in any year, unless otherwise approved in writing by the Local Planning Authority;
16.
Development shall be implemented in full accordance with the approved details of temporary structures required during the construction process, proposals in respect of the public footpath during construction, vehicle wheel washing facility, together with areas for storage of materials and temporary site hoardings. The approved details shall remain in place and in operation for the duration of the construction period;
17.
Prior to the commencement of development, an invasive non-native species protocol shall be submitted to and approved by the local planning authority, detailing the containment, control and removal of Japanese Knotweed on site. The measures within the approved protocol shall be carried out prior to commencement of development unless ongoing control has been approved;
18.
No building shall be occupied until it has been connected to the main drainage system and the approved means of vehicular and pedestrian access thereto have been constructed to a specification and to an extent approved by the Local Planning Authority in relation to that building;
19.
Development shall be carried out in accordance with the approved details of the materials to be used in the construction of the external surfaces of the dwellings; and
20.
The development hereby permitted shall be carried out in accordance with the following approved plans:
2015-15-01, 50, 52, 60, 61, 70, & 71, 2015-15-100, 2015-101; 1210 -130,131,132
2015-15-05M, 2015-15-51B
Reasons:
1.
To protect features of recognised nature conservation importance;
2.
To ensure a satisfactory standard of development;
3.
To ensure a satisfactory form of development in the interests of the visual amenity;
4.
To ensure a satisfactory form of development in the interests of the visual amenity;
5.
To ensure a satisfactory form of development in the interests of the visual amenity;
6.
To ensure a satisfactory form of development in the interests of the visual amenity;
7.
To safeguard the amenity of adjoining residents;
8.
To ensure a satisfactory standard of development;
9.
In the interests of highway safety;
10.
In the interests of highway safety and for the benefit and convenience of the public at large;
11.
To ensure the safety of persons and vehicles entering and leaving the access and proceeding along the highway;
12.
In order that the development site is accessible by non car modes and to meet the objectives of sustainable development;
13.
In the interests of highway safety and the amenities of the area;
14.
To ensure that a reasonable standard of access is provided in the interests of pedestrian and traffic safety;
15.
To protect features of recognised nature conservation importance;
16.
In the interests of the visual and residential amenities of the locality;
17.
To protect features of recognised nature conservation importance;
18.
To ensure that no property is occupied until adequate access and drainage facilities have been provided;
19.
In the interests of the visual amenity of the area; and
20.
For the avoidance of doubt and in the interests of proper planning.
Notes to the Applicant
1.
Failure to comply with any condition imposed on this permission may result in enforcement action without further warning; and
2.
Statement of positive engagement: In dealing with this application Hastings Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the National Planning Policy Framework.
Supporting documents:
- MAP - Land off Robert Tressell Close - HS_FA_16_00710_, item 138c PDF 343 KB
- Land off Robert Tressell Close - HS-FA-16-00710, item 138c PDF 101 KB
-
My council
Contact
Got a question about democratic services?
Content
The content on this page is the responsibility of our Democratic Services team.