Issue - meetings
The Source Kiosk
Meeting: 12/12/2016 - Charity Committee (Item 71)
Minutes:
The Assistant Director (Financial Services and Revenues) presented the report of the Estates Manager, on the update of the position with the lease.
The Source was due to take on the lease for the kiosk 10 working days after practical completion. The kiosk was due to be completed on 14 August 2016, but actual completion was not until 14 October 2016. The Source wish to delay the start of the lease and opening the Kiosk until 1st March 2017 when it is financially more practicable.
Councillor Forward proposed approval of which was seconded by Councillor Cartwright.
RESOLVED (unanimously) that –
1. To note that the kiosk will be opening in March
The reason for this decision was:
There have been delays in constructing the kiosk.
-