White Rock Fountain
Meeting: 09/12/2019 - Charity Committee (Item 55)
White Rock Fountain
Minutes:
Hannah Brookshaw, Regeneration Manger, presented a report to brief the Committee on final progress with the White Rock fountain construction project.
Due to the water ingress mitigation works taking place 4 to 13 December 2019 an urgent decision was taken on 22 November 2019 to agree the recommendation in principle.
It was confirmed that the work is being funded partly from the £12,000 maintenance underspend and partly from savings in other parts of the construction work.
Councillor Forward proposed approval of the recommendation, seconded by Councillor Batsford.
RESOLVED (unanimously):
The committee agree to offset £24,127 to The Source as compensation for lost revenue due to closure of the park for construction works, expected to last 10 days.
Reasons:
Water ingress mitigation works due to leaks caused by construction movement from the new water feature at the area known as White Rock Fountain requires closure of The Source for 10 days to enable works to take place. The compensation to The Source recognises the loss of income to their business during the closure period.
Urgency provisions were utilised and a decision 22 November 2019 due to the time constraints for the requirement for water ingress mitigation works to take place 4 – 13 December 2019, prior to the required reporting process for the next Charity Committee meeting.
-