Decision details
12/13 York Buildings
Decision Maker: Cabinet
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
To consider additional costs
Decision:
1. To increase the budget for this project by £166,000 to £1.011m to meet additional maintenance costs, remedy issues identified when converting the upper floors to 6 flats, and to meet additional contract costs arising from Covid-19.
2. Fund £46,000 of the additional costs from the Renewals and Repairs Reserve with the remaining balance being funded by borrowing.
Report author: Peter Grace
Publication date: 08/12/2020
Date of decision: 07/12/2020
Decided at meeting: 07/12/2020 - Cabinet